A large oil-refinery plant with Liquefied Natural Gas (LNG) storage tanks

Case Study

How we supported the pre-commissioning of an expanded LNG terminal with storage tank inerting, pipeline pre-cooldown, controlled nitrogen supply, and real-time monitoring.

H
i
g
h
l
i
g
h
t

H
i
g
h
l
i
g
h
t

Intero supported the pre-commissioning of an expanded European LNG terminal, where a new LNG storage tank and second unloading jetty had been constructed. The project combined storage tank purging and drying with pipeline inerting and controlled nitrogen pre-cooldown to prepare the system for LNG introduction. 

Download here the case study to read more.

Challenge
Challenge

The client needed to reduce the oxygen concentration in a new LNG storage tank and cool the transfer piping before LNG introduction. This required stable nitrogen flow, careful temperature control, and reliable supply planning throughout the operation. For the pipeline pre-cooldown, Intero had to cool the full piping length while keeping nitrogen in gaseous phase, avoiding excessive temperature differences and reducing the risk of warping or rapid-cooling damage.

Solution
Solution

Intero used steam vaporizers, multiple nitrogen storage tanks, and a vapor/liquid mixing chamber to deliver controlled low-temperature nitrogen gas into the system. Experienced personnel continuously monitored temperature and flow, while close communication with the customer’s control room supported controlled, linear cooling throughout the operation.

Outcome
Outcome

Storage tank inerting was completed within the required timeframe, achieving an oxygen concentration below 8%. Pipeline pre-cooldown also achieved the required result, with temperatures below -100°C at the system extremities. This allowed LNG to be introduced without the risk of rapid-cooling damage to the piping. Real-time monitoring supported precise control of inlet temperature and flow throughout the operation.

LNG plant